Request a proposed sequence of document review, component preparation, fabrication, assembly and agreed inspections where applicable to the offer. The supplier should explain which activities are included and how their completion will be reported. Do not assume that an example schedule represents a confirmed commitment for a new order.
Clarify the decisions needed from the buyer, including any approval of drawings or selection of optional equipment. Ask how late information or changes would be reflected in a revised schedule. Distinguish readiness at the factory from transport, installation or other services that may have separate commercial arrangements.
For discussions with TAIDA GLOBAL, request a dated milestone plan linked to the quotation and record the outstanding assumptions. Comparing the same starting and finishing points gives procurement teams a clearer basis for follow-up, without treating an unconfirmed production estimate as a guaranteed delivery date.